White Stone Bridge

A river crossing in Zhuhai, Guangdong province, China
unfoldTwo entries with the same name
Baishi Bridge is a river crossing connecting Gongbei District and Nanwan District in Zhuhai City, Guangdong Province, China Qianshan River It is an important part of Zhuhai's urban road network, a major transportation project in Zhuhai from 2015 to 2017, and an important content of "Ten Livelihood Facts of Zhuhai Government in 2017 - Improving public Travel Conditions" [1] .
The construction of the White Stone Bridge began on September 20, 2015 [2] ; On June 4, 2017, the first joint pouring work of the East approach Bridge was completed, marking the completion of the main structure [3] ; It opened to traffic on July 30, 2017 [4] .
Baishi Bridge starts from Gangchang Road in the east to Maofeng Road in the west; With a total length of 1387.2 meters and a width of 25.5 meters, the bridge floor is a two-way four-lane urban main road with a design speed of 40 km/h [4] .
Chinese name
White Stone Bridge
Foreign name
BaishiBridge
Date of construction
September 20, 2015
Opening time
July 30, 2017
Subordinate region
Zhuhai City, Guangdong Province, China
length
1387.2 meters
breadth
25.5 m
Lane setting
Two-way four-lane
Design speed
40 km/h
Start-stop position
Gangchang Road, Mau Fung Road
Via route
Gangsan Road, Pingwan Road

Historical evolution

broadcast
EDITOR
The construction of White Stone Bridge
In the 1990s, there were calls to build a new river crossing on the Qianshan River.
After 2000, due to the needs of urban development, a new river crossing in Qianshan River was put on the government's planning agenda.
On March 25, 2014, Zhuhai Transportation Bureau held a public hearing on the project of Baishi Bridge [5] . On June 6, Baishi Bridge was approved by Zhuhai Development and Reform Bureau for the Baishi Bridge project [6] .
On June 29, 2015, White Stone Bridge held public bidding activities. On July 31, the White Stone Bridge again conducted public bidding activities [7] . On September 20, the construction of the White Stone Bridge began. On October 31, Baishi Bridge completed its trestle construction. On November 23, the construction of the No.3 pier of Baishi Bridge began [2] . On December 11, the construction of the Baishi Bridge started.
On August 31, 2016, Baishi Bridge completed the concrete pouring of the second cast-in-place box girder of the West Bund approach Bridge [8] .
On February 28, 2017, Baishi Bridge completed the top tower column of Pier 4 of the main bridge [9] . On May 27, the self-anchored suspension bridge of Baishi Bridge completed the system conversion [10] . On June 4, the Baishi Bridge completed the first joint pouring work of the east approach bridge, marking the completion of the main structure [3] . On July 23, the construction of the Baishi Bridge was completed [11] . On July 30, the White Stone Bridge was completed and opened to traffic, and the opening ceremony was held [4] .

Bridge location

broadcast
EDITOR
Baishi Bridge is located in Zhuhai City, Guangdong Province, China, connecting Gongbei area and Nanwan area, north of the upstream Qianshan Bridge Two miles south and downstream Changsheng Bridge 1.1 km. The starting point is located near the intersection of Pingwan Road and Maofeng Road on the west side of Qianshan River, crossing Qianhe West Road Qianshan River After crossing Qianhedong Road, the end point is at the intersection of Gangsan Road and Gangchang Road on the east side of Hedong [4] .
White stone Bridge at night

Architectural design

broadcast
EDITOR

Building structure

  • Overall layout
Baishi Bridge is composed of main bridge, bridge tower, suspension cable, sling, approach bridge and ramp, and the main bridge section is arranged in the southwest to northeast direction [12] .
  • Design concept
The main tower and bridgehead of the white Stone Bridge adopt European architectural style and are designed in Gothic style [2] , from Archway of Dasanba, Macau Abstract and process the elements of European Gothic architectural style such as spire, arch and beam column to conceive the shape design of the main tower [12] . The section of the tower column is rectangular with a number of convex columns, and the design of the steel structure on the upper part of the tower column cleverly covers the saddle, which not only creates its own landscape but also realizes the functional needs Renaissance The construction method inherited by the building also contains modern style, which combines with the modern cultural atmosphere of Zhuhai to produce a new European architectural style [1] .
White stone Bridge at night
  • Design feature
Baishi Bridge is the first self-anchored suspension bridge in Zhuhai. The main tower adopts "H" frame concrete structure, designed as double-tower superimposed beam self-anchored suspension bridge, and the approach bridge structure is prestressed concrete continuous box girder of equal height [13] . The upper and lower beams and decorative arch rings are arranged between the tower columns, and the four corners of the outer surface of the upper tower columns are provided with landscape decorative columns and the top saddle. The lower tower column is a solid round end section, the upper tower column is a solid rectangle and a decorative arc section is set at the four corners, the upper and lower beams are a single box and single room section, and the decorative arch ring is a solid rectangular section. Among them, the lower beam is a prestressed concrete structure, the top saddle is a steel structure, and the rest is an ordinary reinforced concrete structure [12] .

Design parameter

White stone Bridge day view
The total length of the Baishi bridge is 1387.2 meters, of which the bridge is 805 meters long (the main bridge is 330 meters long, the approach bridge is 475 meters long), the approach is 301 meters long, the connecting road is 281.2 meters long, and the bridge span is arranged as (30+60+150+60+30) =330 meters [12] ; The second link of the west approach bridge is 3×32.5 meters on the shore, with a full width of 16.5 meters and the whole layout; The first link of the West Approach Bridge is 40 meters +3x50 meters in the water, with a full width of 25.5 meters and a whole layout [1] The tower above the bridge floor is about 44 meters high. Sidewalks and non-motorized lanes are provided on both sides [4] . The full height of the main tower is 62.26 meters, the transverse center distance of the tower column is 28.5 meters, and the transverse clear distance is 25.56 meters. The lower tower is 11.2 meters high, the transverse bridge width is 4.1~4.5 meters, and the transverse bridge width is 3 meters. The upper column is 28.9 meters high, the transverse bridge width is 2.8 meters, and the transverse bridge width is 2.8 meters. The top decoration saddle is 15.8 meters high; The lower beam is 3 meters high, 2.8 meters wide and 60 centimeters thick; The upper beam is 3 meters high, 2.8 meters wide, and the wall is 40 centimeters thick [12] .
Technical standard
Grade of road
Urban trunk road
Lane setting
Two-way four-lane
Design speed
40 km/h
Design basis
100 years
Design load
Bridge: City -A class; Crowd: 3.5 kN/m2
Flood control standard
Once in a hundred years, water level 1.674 meters (highest navigable water level)
Design wind load
Once in a hundred years 38.4 m/s
Channel class
Inland waterway Class IV
Channel standard
The single hole width is 90 meters, the single side of the double hole is 45 meters, and the clear height is 8 meters
Seismic intensity
Set up at seven degrees
Reference materials: [1] [4]

Facilities and equipment

broadcast
EDITOR
  • Sightseeing elevator
As of July 2017, two sightseeing elevators have been set up at the upper and lower Bridges of the East and West roads in front of the Baishi Bridge, which can be used for pedestrian sightseeing [4] .

Operation situation

broadcast
EDITOR
  • Fare system
On July 30, 2017, the White Stone Bridge opened to traffic, and the bridge is free of charge [4] .

Construction achievement

broadcast
EDITOR
  • Technical difficulty
The difficulties faced by the White Stone Bridge and the construction technology and characteristics adopted are as follows:
1, the white stone bridge is built in accordance with the landmark bridge standard, not only the appearance of fashion, but also the technical content is relatively high, and the cable is complex to go through a lot of calculations [2] .
2. In the construction process of Baishi Bridge, the construction site is small, the traffic organization is difficult, the construction area is complicated, the construction coordination is difficult and other difficulties [14] .
3. In the design of the main tower structure of Baishi Bridge, the concept of mechanics directly guides the design direction, quickly stabilizes the structure size of the main tower and improves efficiency. Except for the main tower of suspension bridge, the method is also applicable to the compression structures with fuzzy boundary conditions such as cable-stayed bridge and pier.
4. Set the saddle cushion stone at the top of the tower, and use the space to reduce the cable saddle volume. The weight of the saddle is reduced by 51%, which directly saves the project cost; At the same time, it reduces the difficulty of cable saddle factory manufacturing, shipping and transportation, on-site installation and other links. Compared with the traditional method, this method has outstanding advantages and is universal to the design of the connection between the top of the suspension bridge tower and the cable saddle [12] .
White stone Bridge evening

Value meaning

broadcast
EDITOR
The Baishi Bridge is of great help to alleviate the congestion of Qianshan Bridge and divert the existing traffic pressure. As a quick channel connecting Gongbei area and Nanwan area, connecting the two separate coastal areas into one is conducive to promoting the economic development of Gongbei and Nanwan and even the western district, and integrating the economic center of Zhuhai [2] . (Review by Southern Metropolis Daily)
The completion of the Baishi Bridge can not only relieve the traffic pressure of the existing Bridges across the Qianshan River in Zhuhai, but also accelerate the construction of the regional road network, regional economic integration, promote the construction of Zhuhai as a "core city on the west bank of the Pearl River Estuary", strengthen the connection of regional groups, and accelerate the economic development of the western region [1] . (Comment on the First Design Institute of China Railway Bridge Survey and Design Institute Group Co., LTD.)
The White Stone Bridge is an important project to shape the image of the city and improve the quality of the city. It connects the central city of Wanchai and Nanping, Zhuhai, and becomes an important new channel across Qianshan River, effectively realizing the seamless connection between the two sides of Qianshan River. The completion of the Baishi Bridge can effectively relieve the increasingly saturated traffic pressure of Zhuhai Qianshan Bridge and Changsheng Bridge, which is of great practical significance to further improve the traffic condition of Zhuhai and speed up the economic development of Zhuhai [14] . (Comments of China Railway Bridge Group Co., LTD.)
White stone Bridge at night